Here are the latest updates from the project manager regarding Construction Phase Stage 2 on Bird Ave. between Coe Ave. and Willow St.
The contractor began work on Stage 2 of this project on Monday, Dec. 9th. The contractor has completed the installation of 190 linear feet of new sanitary sewer pipe, 720 linear feet of new storm sewer pipe, 5 new manholes and 3 new storm inlets. This completes the replacement of the older existing sanitary and storm sewer systems on this section of Bird Ave.
Over the last week, the contractor has been working on the demolition of the existing curb & gutter and sidewalk on the west side of Bird Ave. New curb & gutter and new sidewalk will be constructed over the remainder of this week and next week.
Over the next month, the contractor will be completing the replacement of sections of the curb & gutter and sidewalk, removing sections of the old roadway, and replacing these sections with new roadway.
You can find abbreviated project updates on Twitter. You can access this project information at “SJ Bird Ave Project” or, search for #SJBirdAve on Twitter.